|
Tendering
of the Notice of Readiness
(“NOR”) is one area that many
owners can so easily slip up.
If the vessel is subsequently
delayed, a sloppy tender of the
NOR can cost an owner dearly when
he calculates laytime and
demurrage resulting in not
insubstantial losses.
This
is what happened to the owners of
the “The Happy Day” recently
(see Glencore Grain Ltd v Flacker
Shipping Ltd - QBD (Com Ct)
(Langley J) ) - 25 January 2001).
This High Court decision arose
from an appeal to an award in
arbitration. The question
was :
“What
were the rights of the owners to
demurrage and charterers to
despatch when a charterparty
provided for a notice to be given
at the discharge port to trigger
the start of laytime but only an
invalid notice was given, and yet
the vessel commenced and completed
discharge over an extended period
in circumstances in which a
substantial claim to demurrage
would otherwise have arisen?”
The
vessel was chartered on an amended
Synacomex form for the carriage of
a cargo of wheat to be discharged
at the average rate of 1,500 mt
per weather working day of 24
consecutive hours pro rata,
laytime to be
non-reversible.
Clause
30 provided that at first or sole
discharging port, notice was to be
given to receivers/agents during
normal local office hours and
laytime was to start counting at 8
am next working day whether in
berth or not, whether in port or
not, whether in free pratique or
not, whether in customs cleared or
not, time from Friday 5 pm until
Monday 8 am not to count even if
used.
The
vessel completed loading 23,000 mt
of wheat at Odessa and on arrival
Cochin on 25 September at 1630H
was unable to immediately enter
the port as she had missed the
tide. Nevertheless, the
Master purported to tender NOR at
1630H that day.
The
vessel only entered the port the
next day at 1016H, berthing at
1315H. No further NOR was
tendered. Discharge
commenced on 26 September and only
completed on 25 December.
The Statement of Facts (“SOF”)
was signed by both vessel’s and
receiver’s agents which recorded
that NOR was tendered and accepted
at 1630H on 25 September.
The
owners claimed demurrage while the
charterers said that lay-time
never commenced since NOR was not
validly tendered and claimed
despatch.
The
arbitrators held among other
things, that the NOR was not
marked “accepted” but
“received” even though the SOF
said that NOR was “accepted”
and that lay-time did not start
unless the charterers conceded
otherwise. Nevertheless, the
arbitrators still concluded that
lay-time commenced at 0800H on 29
September.
The
charterers appealed to the High
Court. Langley J referred to
the decision of Mustill LJ in
“The Mexico 1” [1990] 1
Lloyd’s Rep 507 and confirmed
the position that an invalid
notice could not be treated as
“inchoate” - becoming
effective when the vessel was
ready for discharge at some other
time from which it was originally
contracted to become effective.
In order to do so, one had to look
at some kind of bilateral
representation and action on the
basis that the contractual
arrangement had been replaced by
something new.
The
fact that the SOF had said that
the NOR had been “accepted”
was not enough. There had to
be something clearer and
unequivocal between the parties to
indicate that the terms of the
charterparty had been varied by
mutual consent.
Just
because discharge commenced did
not validate an invalid notice to
comply with clause 30 since that
would be inconsistent with the
judgement of Mustill LJ in “The
Mexico 1” rejecting the concept
of an inchoate notice.
Neither
was it possible to infer any
agreement or convention just
because discharge had commenced or
continued and that the invalid
notice was not rejected.
It
would not necessarily follow from
that that charterers had chosen to
give up their rights to a valid
notice in accordance with the
terms of the charterparty unless
clause 30 had contained additional
words like “and in any event,
lay-time to commence when
discharge starts”.
In
the circumstances, the owners were
not entitled to demurrage and the
charterers claim for despatch
succeeded.
This
case very clearly shows that
owners must instruct their Masters
to follow the provisions with
regard to the tender of the NOR
set out in the charterparty to the
letter.
Any
deviation from those provisions,
no matter how slight, could render
the NOR invalid. If there is
any doubt whatsoever on the owners
part that the tender of the NOR
was invalid, it is always safer to
re-tender the NOR although one
must still be careful that the
re-tender does not invalidate what
would have otherwise been a valid
tender of the earlier NOR.
Alternatively,
owners would be well advised to
seek clear written confirmation
from the charterers that they
accept as valid the tender of the
NOR rather than just leaving it to
an indication in the SOF.
This
is a minor point and something
which an operations or post
fixture man in owners office can
so easily overlook. The
result may very well cost owners
dearly.
|